目前,河南电网尖峰负荷持续时间短,且尖峰负荷远远高于日常最大负荷,实施电力需求侧响应可有效提升电网运行效率,减少电网、电源投资。为了高效实施电力需求侧响应,可提前对全省主要用户削峰潜力进行评估,通过用户削峰潜力大小可快速锁定参与响应的用户。本文详细介绍了削峰潜力评估流程和方法,以期对其他地区开展电力需求侧响应有一定的参考。
<<At present,the peak load duration of Henan Power Grid is short,and the peak load is much higher than the daily maximum load. Implementing the power demand side response can effectively improve the grid operation efficiency and reduce the grid and power investment. In order to efficiently implement the power demand side response,the peak potential of the main users in the province can be evaluated in advance,and the users who participate in the response can be quickly locked by the user’s peak potential.
<<Keywords: | Henan ProvincePower Demand Side ResponsePeak Clipping Potential AssessmentLoad Characteristics |